Plan Pluriannuel de Travaux: Rules for French Condos

By Ilia SotoninPpt, Copropriete, Maintenance plan
Plan Pluriannuel de Travaux: Rules for French Condos

Yes, the plan pluriannuel de travaux (PPT) is mandatory for French condominiums (copropriétés), but what the law makes compulsory is the draft plan (projet de PPT). Article 14-2 of the law of 10 July 1965 requires the draft to be prepared in any copropriété whose building is wholly or partly residential, once the building is fifteen years past the reception of its construction works, to be presented to the general meeting and, if it shows works needed within ten years, to be put to a vote for adoption, and to be updated every ten years. Adoption itself is not compulsory: the text requires the vote, not its outcome. One exemption: if a diagnostic technique global shows no need for works within ten years, the syndicat does not have to prepare the draft. The phase-in dates by number of lots (2023, 2024, 2025) have passed, so as of November 2026 every copropriété in scope is covered. The law names no fine for not having a plan; it lets the administrative authority have one drawn up at the syndicat's expense in certain cases. We checked the text on 2 November 2026 on Légifrance. This is general information, not legal advice.

Who needs a PPT, and since when

The text covers buildings "à destination partielle ou totale d'habitation soumis à la présente loi", meaning copropriétés with at least some residential use. The trigger is age: fifteen years from the reception of the construction works. The draft is then "actualisé tous les dix ans".

Article 171, VI, of the law of 22 August 2021 phased it in:

  • more than 200 lots: 1 January 2023;
  • 51 to 200 lots: 1 January 2024;
  • 50 lots or fewer: 1 January 2025.

The text counts lots used as housing, offices or shops. In the passage we read it does not say how cellars and parking spaces are counted: if you sit close to 50 or 200, ask your syndic or your local ADIL (the departmental housing information agency) to confirm the count.

One exemption: if a diagnostic technique global (DTG) shows no need for works in the ten years after it is drawn up, the syndicat does not have to prepare a draft PPT.

What the draft PPT contains

The draft is built from an analysis of the building and its equipment, the energy performance diagnosis and, if one exists, the DTG. It contains:

  1. the list of works needed to safeguard the building, protect occupants' health and safety, save energy and reduce greenhouse gas emissions;
  2. an estimate of the performance level those works can reach;
  3. a summary cost estimate and a ranking of the works;
  4. a proposed timetable for the works needed in the next ten years.

It must be prepared by a person with the skills and guarantees set out in a decree. We did not re-read that decree for this page, so ask any provider to document theirs.

The prescribed works and timetable then go into the building's maintenance logbook (carnet d'entretien).

The vote: what the syndic must put on the agenda

The law sets three steps, all in front of the general meeting:

  1. How the draft is prepared goes on the agenda and is voted by "la majorité des voix exprimées des copropriétaires présents, représentés ou ayant voté par correspondance", that is, the votes cast by owners present, represented or voting by post.
  2. The draft is presented at the first meeting after it is drawn up or revised. If it shows works needed within ten years, the syndic puts adoption of all or part of it to a vote, which needs "la majorité des voix de tous les copropriétaires": a majority of all owners' votes, not just those cast.
  3. After that, every meeting that approves the accounts returns to it: either adoption of the draft, if not yet adopted, or the decisions to carry out the timetable of the adopted plan.

Note what the text does and does not say. It requires the draft to be prepared and put to a vote. It does not say the meeting must adopt it.

What if the copropriété has no PPT?

Article 14-2 names no fine. What it does provide: under the building safety and sanitation powers, the administrative authority can at any time ask the syndic for the adopted plan. If the plan is not sent within a month, or manifestly does not prescribe the works needed for occupants' safety, the authority may "élaborer ou actualiser d'office le projet de plan pluriannuel de travaux, en lieu et place du syndicat des copropriétaires et aux frais de ce dernier". The syndic then calls a meeting to vote on it.

When a lot is sold, the adopted plan (or, failing that, the draft if one was prepared) is among the documents handed to the buyer at the latest when the promise of sale is signed (Code de la construction et de l'habitation, article L721-2).

What to do, in order

  1. Find the date the construction works were accepted and count the lots.
  2. Ask the syndic in writing whether a DTG, a PPT or a draft PPT already exists, and where its agenda item stands.
  3. Ask the syndic to put the preparation terms on the agenda of the next meeting, with two or three comparable quotes.
  4. Have the draft prepared by someone who can document their skills and guarantees.
  5. Present it at the following meeting and vote on adopting all or part of it.
  6. Enter the works and timetable in the maintenance logbook and keep the follow-up on the agenda of every accounts meeting.

What this page does not say

We did not read the decree on the skills of the person who prepares the draft, nor what a DTG contains. Costs and subsidies are out of scope. So are special rules for France's overseas territories. Your own règlement de copropriété may add rules about works.

What Unitify does, and what it does not

Unitify does not write a PPT and does not replace the provider who prepares it or the general meeting. It helps around it: keeping diagnostics, quotes and minutes in one place per building; tracking owners' requests as tickets; posting a reminder of the meeting in the resident app, on top of the legal notice; recording votes where your rules allow it. The tool records votes; whether a vote is valid depends on the law and your règlement, not on the software. See also Unitify in France and the guide to a general meeting notice.

Book a demo

Sources

Topics:PptCoproprieteMaintenance plan

Frequently asked questions

Is the plan pluriannuel de travaux mandatory in 2026?

Yes, for a copropriété whose building is wholly or partly residential and is more than fifteen years past the reception of its construction works. Article 14-2 of the 1965 law requires a draft multi-year works plan to be drawn up à "l'expiration d'un délai de quinze ans à compter de la date de réception des travaux de construction de l'immeuble" and updated every ten years. What is compulsory is the draft: preparing it, presenting it to the general meeting and, if it shows works needed within ten years, putting its adoption to a vote. Adoption itself is not compulsory. There is one exemption: a diagnostic technique global that shows no need for works within ten years. The three phase-in dates by size (2023, 2024, 2025) have all passed.

From when does the PPT apply, by number of lots?

From 1 January 2023 for more than 200 lots, 1 January 2024 for 51 to 200 lots, and 1 January 2025 for 50 lots or fewer (article 171, VI, of the law of 22 August 2021). The text counts lots "à usage de logements, de bureaux ou de commerces"; it does not say whether cellars and parking spaces count, and we do not interpret it.

My building is less than fifteen years old. Does the PPT apply?

The draft plan is required once fifteen years have passed since the construction works were accepted. Before that the law does not require it. Check the date the works were accepted, not the date of the sale or of the creation of the copropriété.

What goes into a PPT?

According to article 14-2: the list of works needed to safeguard the building, protect the occupants' health and safety, save energy and cut greenhouse gas emissions; an estimate of the performance level those works can reach; a summary cost estimate with priorities; and a proposed timetable for the works needed in the next ten years.

Who votes the PPT, and with what majority?

The general meeting. How the draft is prepared is voted by "la majorité des voix exprimées des copropriétaires présents, représentés ou ayant voté par correspondance"; adopting all or part of the draft requires "la majorité des voix de tous les copropriétaires". The syndic must put both questions on the agenda.

What is the penalty if a copropriété has no PPT?

Article 14-2 names no fine and no amount. It provides that, under the building safety and sanitation powers, the administrative authority can ask the syndic for the adopted plan and, if it is not sent within a month or manifestly does not prescribe the works needed for safety, draw up the draft itself at the syndicat's expense.

What is the difference between the PPT and the diagnostic technique global?

The diagnostic technique global (DTG) is a separate document that the general meeting decides on (article L731-1 of the Code de la construction et de l'habitation). The PPT can build on it. If a DTG shows no need for works over ten years, the syndicat is exempt from drawing up the draft PPT.

Does the seller have to give the PPT to a buyer?

Yes, when a lot in a wholly or partly residential building is sold: the adopted plan, or failing that the draft if one exists, is among the documents handed to the buyer at the latest when the promise of sale is signed (article L721-2 of the Code de la construction et de l'habitation).