Dubai Building Handover Checklist Template

By Ilia SotoninDubai, Handover, Developers, Template

Only the checklist prints; the rest of this page is hidden. In the print dialog, choose "Save as PDF" to download it. Free, no sign-up.

The handover of a jointly owned building to its management company is where the files, the money and the liabilities change hands, and in Dubai each of them has a rule behind it. The checklist below follows Law No. (6) of 2019 and RERA's circular on handover records. It is a model, not legal advice: have your adviser review it before you use it. This page describes Dubai; Abu Dhabi has its own law and its own regulator, ADREC. For the rest of a management company's day-to-day paperwork, see how Mollak fits.

Before you use it

  • Who acts. The developer files the documents with the Dubai Land Department, delivers the handover records and, until RERA appoints a Management Company, manages the property and keeps the service charges paid by owners in the property's Service Charges account. The receiving party is the management company: selected and contracted by RERA in a project that is neither a major project nor a hotel project, or contracted by the developer in a major project under an agreement RERA approves. Where there is no developer in a major or hotel project, RERA selects the company (art. 18).
  • What starts the clock. The completion certificate: the developer files the documents within sixty days from the date it is issued, and the Dubai Land Department may extend that by up to thirty days for valid reasons it accepts. The developer's liability for defects also runs from it, ten years for the structural parts. The texts we read set no deadline for the handover from a developer to a management company, so the form records the dates you agree. (When RERA replaces a management company, it sets the period for handing the property to the new one, RERA Circular No. (4) of 2020.)
  • What must all hold. The documents are four: the Plans, the Master Community Declaration, the Statute and the Building Management Regulation; the developer does not file the last where RERA prepared it. The checklist has a line for each.
  • Who signs. The texts we read name no signatory for a handover record. The form has a line for the developer's authorised representative and one for the management company's, and a line for the reference of RERA's appointment or approval.

What the law says

  • Four documents form part of the title deed.

"The Plans, Master Community Declaration, Statute, and Building Management Regulation will constitute part of the title deed of Jointly Owned Real Property. The DLD will maintain an original copy of each of these documents." (Law No. (6) of 2019, art. 6(a))

  • The developer files them within sixty days.

"within sixty (60) days from the date of issue of the completion certificate. The DLD may extend this time limit for a period not exceeding thirty (30) days, provided that the Developer provides valid reasons for the extension that are acceptable to the DLD." (art. 6(c))

"The Developer's obligation under paragraph (c) of this Article does not include filing the Building Management Regulation where it is prepared by RERA." (art. 6(d))

  • Handover records.

"The developer is obligated to deliver the documents related to the delivery and handover of units to the buyers. These documents are considered records of the property, and service fees are calculated based upon them." (RERA Circular No. (3) of 2021)

  • The developer keeps the money until a company is appointed.

"Until a Management Company is appointed by RERA, the Developer must undertake the management of the Jointly Owned Real Property and maintain the Service Charges paid by Owners in the relevant Service Charges account, as prescribed by this Law." (art. 30(d))

  • The developer's own share.

"A Developer will pay his share of the annual Service Charges in respect of unsold Units, and in respect of the sold Units for which he undertakes, under the provisions of the sale contract or reservation agreement, to pay the Service Charges on behalf of the purchaser." (art. 25(a))

  • Outsourcing needs RERA's approval.

"The Developer may outsource all or any of his duties, and delegate all or any of his responsibilities, under sub-paragraph (a)(1) of this Article to a Management Company in return for the fees, and subject to the conditions, agreed upon by both parties. This agreement must be approved by RERA." (art. 18(c))

  • Insurance and the guarantee fall on the Management Entity. "A Management Entity must insure the Jointly Owned Real Property under an insurance policy that covers the maintenance and reconstruction of the Jointly Owned Real Property in case of fire, damage, or destruction for any reason whatsoever" (art. 41(a)), and "A Management Entity must provide a bank guarantee, in favour of the DLD and in the amount it determines" (art. 36(a)). The amount is the Dubai Land Department's to set; the checklist asks only for the date the guarantee was provided.
  • Mollak. Its process page lists management registration, community registration, the management agreement and the bank account as steps one to four, and says "It is mandated to establish regulated bank accounts approved by DLD".
  • The developer remains liable.

"a developer will remain liable, for a period of ten (10) years from the date of obtaining the completion certificate of the Real Property project developed by him, to remedy or rectify any defects in the structural parts of the Jointly Owned Real Property." (art. 40(a))

The handover checklist

HANDOVER CHECKLIST: DEVELOPER TO MANAGEMENT COMPANY, JOINTLY OWNED PROPERTY IN DUBAI
[General model. Check it against your own documents and your adviser before you rely on it, and delete this line.]

Project: [____]    Building or plot: [____]    Number of units: [__]
Category of the project (Law No. (6) of 2019, art. 18): [major project / hotel project / project that is neither]
Developer: [____]
Receiving management company: [____]
Basis of the company's role: [selected and contracted by RERA, reference ____ / outsourced by the developer under an agreement approved by RERA, reference ____ / outsourced by the developer to a hotel project management company (hotel project), reference ____ / selected by RERA because there is no developer, reference ____]
Date of the completion certificate: [__/__/____]    Date of this handover: [__/__/____]

1. Documents filed with the Dubai Land Department (art. 6)
Sixty days from the completion certificate end on: [__/__/____]
Extension granted by the Dubai Land Department: [none / up to thirty days, until __/__/____]
Plans: [filed on __/__/____ / not filed]
Master Community Declaration: [filed on __/__/____ / not filed]
Statute: [filed on __/__/____ / not filed]
Building Management Regulation: [filed on __/__/____ / prepared by RERA, not filed by the developer]

2. Records of the property (RERA Circular No. (3) of 2021)
Documents on the delivery and handover of units to the buyers: [handed over on __/__/____ / pending]
Handover notice dates, unit by unit: [attached / pending]

3. Registration in Mollak
Management company registered in Mollak: [yes / no]
Community registered as a property group: [yes / no]
Management agreement assigned through Mollak: [yes / no]
Regulated bank account created: [yes / no]    Bank: [____]

4. Service charges
Service charges account of the property: [bank, account name]
Service charges paid by owners before handover, in the Service Charges account: [balance on __/__/____: ____]
Cash reserve account, separate from it: [bank, account name]
Developer's share for unsold units, and for sold units where he undertook to pay: [settled up to __/__/____]
Budget: [approved by RERA / temporary budget / to be submitted]    Period: [____]

5. Insurance and guarantee (arts. 41 and 36)
Insurance policy for maintenance and reconstruction, with the Management Entity as beneficiary: [insurer, policy number, period]
Insurance against liability for damage and bodily injury: [insurer, policy number, period]
Bank guarantee in favour of the Dubai Land Department: [provided on __/__/____ / to be provided]

6. The developer's continuing liability (art. 40)
Structural parts, ten years from the completion certificate, until: [__/__/____]
Defective installations, one year from the handover of each unit, or from the completion certificate where the owner refrained from taking possession: [unit-by-unit dates attached]
Known defects at handover: [list attached / none]

Handed over by the developer's authorised representative: [name, position]    Signature: ______________________    Date: ____________
Received by the management company's authorised representative: [name, position]    Signature: ______________________    Date: ____________
Reference of RERA's appointment or approval: [____]

How Unitify helps

Fill in the form by hand or in Word. Unitify helps with what happens around it: once the building is handed over, owners are invited to the resident app, where they see their charges and send requests, and defects found after handover are logged with their dates for the management company and the developer.

See the UAE page, the pricing page or book a demo.

Sources: Law No. (6) of 2019 Concerning Ownership of Jointly Owned Real Property in the Emirate of Dubai, Dubai Legislation (dlp.dubai.gov.ae), accessed 2026-09-07 and 2026-11-28; RERA Circular No. (3) of 2021, Dubai Land Department; Mollak's process page, mollak.dubailand.gov.ae, accessed 2026-09-07. This covers Dubai.

Sources

Topics:DubaiHandoverDevelopersTemplate

Frequently asked questions

What must a Dubai developer file and hand over?

Within sixty days of the completion certificate the developer files the Plans, the Master Community Declaration, the Statute and the Building Management Regulation with the Dubai Land Department (Law No. (6) of 2019, art. 6; the Building Management Regulation is not filed by the developer where RERA prepared it). RERA Circular No. (3) of 2021 adds that the developer delivers the documents on the delivery and handover of units to the buyers, which are the records of the property. The checklist below lists both.

Who manages the building until a management company is appointed?

Until a Management Company is appointed by RERA, the developer must undertake the management of the jointly owned property and maintain the service charges paid by owners in the service charges account (art. 30(d)).

Who appoints the management company?

It depends on the category of the project. In a major project the developer is responsible for management and may outsource its duties to a Management Company under an agreement that RERA must approve. In a project that is neither a major project nor a hotel project, a specialised management company is selected and contracted by RERA. In a hotel project the developer must outsource the management to a hotel project management company, and where there is no developer in a major or hotel project, RERA appoints the Management Company (art. 18).

What happens if the developer files the documents late?

The Dubai Land Department may extend the sixty days by up to thirty days if the developer gives valid reasons it accepts. Where the documents are not filed in time, it may ask any entity to file and maintain them, and the developer is liable for the expenses and costs (art. 6).

Does the developer stay liable after handover?

Yes, for defects in the structural parts for ten years from the date of the completion certificate, and for defective installations for one year from the handover of the unit to the owner, or from the completion certificate if the owner refrains from taking possession (art. 40). This page describes Dubai; Abu Dhabi has its own law.