Skip to content
Unitify
Free template

Section 20 notice of reasons: template for England (Word, PDF)

By Ilia Sotonin

Opens your browser's print dialog: choose a printer or "Save as PDF". Only the form is printed. Free, no sign-up.

Keep the signed notice and the leaseholders' list with the building in Unitify, free and with no card.

Start free

Get this document with your building’s details filled in

Tell us the building and we write it into the Word file for you. The blank files above stay free to download.

The notice of reasons is the last written step of the section 20 consultation for qualifying works in England. Under paragraph 6 of Schedule 4, Part 2 of the Service Charges (Consultation Requirements) (England) Regulations 2003 the landlord who enters into a contract for the works must, within 21 days of entering into the contract, give notice in writing of its reasons for awarding it, or say where a statement of the reasons may be inspected, and summarise any observations it had to have regard to and its response.

It is a model, not an official form: the regulations list the contents and prescribe no wording. The landlord gives it, which can be a freeholder, a residents' management company or a right to manage company. It covers England only and works where public notice is not required. This is general information, not legal advice.

When must the landlord give the notice of reasons?

Paragraph 6(1) of Part 2 of Schedule 4 sets the duty and the clock:

  • Subject to sub-paragraph (2), where the landlord enters into a contract for the carrying out of qualifying works, he shall, within 21 days of entering into the contract, by notice in writing to each tenant and the recognised tenants' association (if any)—

    Schedule 4, Part 2, paragraph 6(1), SI 2003/1987, legislation.gov.uk

The 21 days run from entering into the contract. The notice goes to each tenant and to the recognised tenants' association, if there is one.

What must the notice contain?

The regulations list two things:

  • state his reasons for awarding the contract or specify the place and hours at which a statement of those reasons may be inspected; and

    Schedule 4, Part 2, paragraph 6(1)(a), SI 2003/1987, legislation.gov.uk
  • summarise the observations and set out his response to them.

    Schedule 4, Part 2, paragraph 6(1)(b), SI 2003/1987, legislation.gov.uk

The second item applies where the landlord received observations it was required to have regard to. Where a statement is left for inspection, paragraph 2 applies to it as it applies to a description of the works: reasonable place and hours, free of charge, a free copy on request if copying is not offered (paragraph 6(3)).

When is the notice not needed?

Paragraph 6(2) removes the duty in two cases:

  • The requirements of sub-paragraph (1) do not apply where the person with whom the contract is made is a nominated person or submitted the lowest estimate.

    Schedule 4, Part 2, paragraph 6(2), SI 2003/1987, legislation.gov.uk

The word is "or": a nominated person, or the person who submitted the lowest estimate, is enough. A nominated person is one whose name was proposed in response to the invitation in the notice of intention.

Who gives the notice?

The landlord, as the regulations and the Act use the word:

  • “landlord” includes any person who has a right to enforce payment of a service charge

    Section 30, Landlord and Tenant Act 1985 (definition of "landlord"), legislation.gov.uk

For a right to manage company, paragraph 4 of Schedule 7 to the Commonhold and Leasehold Reform Act 2002 reads the references to the landlord in sections 18 to 30 as references to the company. The regulations name no signature and no method of service beyond "in writing".

Does this apply everywhere in the UK?

No. The regulations say:

  • These Regulations apply in relation to England only.

    Regulation 1(2), SI 2003/1987, legislation.gov.uk

Wales, Scotland and Northern Ireland are not covered by this page.

Sources

Checked against legislation.gov.uk on 28 November 2026. Legislation changes: check the current text before acting. England's service charge rules are being changed in stages by the Leasehold and Freehold Reform Act 2024, with provisions coming into force for England on 6 November 2026, 1 April 2027, 1 November 2027 and 1 November 2028 (SI 2026/1128).

Notice of the landlord's reasons for awarding the contract

Section 20, Landlord and Tenant Act 1985 · Schedule 4, Part 2, paragraph 6, Service Charges (Consultation Requirements) (England) Regulations 2003

Building or premises the works are to (name and address)
Landlord giving the notice (freeholder, residents' management company or right to manage company) and its address
Date of this notice
Leaseholder the notice is addressed to (name and flat number)
Recognised tenants' association, if one represents some or all of the leaseholders (secretary)
Contractor with whom the contract was made
Date the contract was entered into

Notice

  1. 1.The landlord named above entered into a contract for the carrying out of qualifying works to the building named above, with the contractor and on the date stated above. This is a notice given to you under paragraph 6 of Schedule 4, Part 2 of the Service Charges (Consultation Requirements) (England) Regulations 2003, in the consultation required by section 20 of the Landlord and Tenant Act 1985.
  2. 2.This notice is given to each leaseholder and, where there is a recognised tenants' association, to the association.

How the reasons are given (tick one)

  • The landlord's reasons for awarding the contract are stated below
  • A statement of those reasons may be inspected at the place and during the hours stated below

The landlord's reasons for awarding the contract

Place and hours at which a statement of the reasons may be inspected (reasonable place and hours, free of charge)

Observations on the estimates (tick one)

  • The landlord received observations it had to have regard to: a summary and its response are below
  • The landlord received no such observations

Summary of the observations received and the landlord's response

When this notice is not needed (ours)

  1. The requirement does not apply where the person with whom the contract is made is a nominated person or submitted the lowest estimate: either one is enough. Use this notice only when the contractor is neither.
  2. Give the notice within 21 days of entering into the contract, to each leaseholder and to the recognised tenants' association, if there is one.

Landlord, or the person signing on its behalf

Name, role, signature and date

Model prepared by Unitify as a reference. It is not a prescribed or official form and not legal advice: paragraph 6 of Schedule 4, Part 2 lists what the notice must contain and sets no wording. England only. Have a solicitor check it for your building, and check the lease for how a notice must be served.

How to use the template, and when it is needed

  1. 1

    Check that the notice is needed

    It is not needed where the person with whom the contract is made is a nominated person or submitted the lowest estimate. Either condition removes the duty, so the notice is needed only where the contractor is neither.

  2. 2

    Count the 21 days from entering into the contract

    The period runs from the day the landlord enters into the contract, not from the day it decides to award it or the date of any letter. Write the date of the contract on the notice and diarise the last day.

  3. 3

    State the reasons, or where they can be inspected

    Either set out the reasons for awarding the contract or give a place and hours where a statement of them may be inspected. The place and hours must be reasonable, inspection free of charge, and a copy free on request where copying is not offered.

  4. 4

    Summarise the observations and give the notice in writing

    Where the landlord received observations it had to have regard to, summarise them and set out the response. Give the notice in writing to each leaseholder and to the recognised tenants' association, if there is one, in the way the leases require, and keep proof.

What to check with your solicitor

This is a model of the reasons notice, not an official form. Before you use it on a real building, check these points.

  • Who the landlord is. Section 30 of the 1985 Act says the landlord includes anyone with a right to enforce payment of a service charge, and for a right to manage company paragraph 4 of Schedule 7 to the Commonhold and Leasehold Reform Act 2002 reads the references to the landlord as references to the company. Whether your residents' management company has that right depends on the leases.
  • The day the contract was entered into, and whether the 21 days include that day: the regulations say "within 21 days of entering into the contract".
  • Whether the contractor was a nominated person or submitted the lowest estimate, and how the lowest estimate is compared when estimates differ in scope.
  • How the lease says a notice must be served on a leaseholder: the regulations say only "in writing".
  • Whether public notice of the works was required (Part 1 of Schedule 4 applies instead) or the works are under a long-term agreement, which needs separate advice.
  • Whether you need a tribunal dispensation because a step was missed, and what a tribunal treats as reasonable.
  • England's service charge rules are being changed in stages by the Leasehold and Freehold Reform Act 2024, with provisions coming into force for England between 6 November 2026 and 1 November 2028. Check the text in force on the day you act.
  • Wales is not covered by this form.
Ready to use

What Unitify does around a section 20 notice

Fill in the form by hand or in Word. Unitify helps with what happens around it:

  • Lease documents and estimates in one place

    Leases, estimates and correspondence can be uploaded and kept with the building's documents. Structured lease records are set up per project.

  • The deadlines as tickets

    You can enter each window and each date from the notice as a ticket with a date in the calendar, so none is missed.

  • An announcement in the resident app

    You can post an announcement in the resident app on top of the legal notice. It does not replace the written notice, which is given as the lease and the law require.

Section 20 notice of reasons: questions

What is a section 20 notice of reasons?

The notice a landlord in England gives after entering into a contract for qualifying works, stating its reasons for awarding the contract (or where a statement of the reasons may be inspected) and, where it received observations it had to have regard to, summarising them and setting out its response.

How long does the landlord have?

Within 21 days of entering into the contract. The clock starts when the contract is entered into, not when the landlord decides to award it.

Is it always needed?

No. The requirement does not apply where the person with whom the contract is made is a nominated person or submitted the lowest estimate. Either one is enough, so the notice is needed only where the contractor is neither.

Who sends it, and to whom?

The landlord, by notice in writing to each tenant and the recognised tenants' association, if there is one. That can be a freeholder or a residents' management company with a right to enforce payment of the service charge; for a right to manage company the references to the landlord are to the company.

Can the reasons be left for inspection instead of being written in the notice?

Yes: the landlord may either state its reasons or specify the place and hours at which a statement of the reasons may be inspected. The place and hours must be reasonable, the statement must be available free of charge, and where copies cannot be taken a copy must be given on request, free of charge.

Is there an official form?

No. Paragraph 6 of Schedule 4, Part 2 lists what the notice must contain and prescribes no wording, so this template is a model.

Does this apply in Wales?

No. These regulations apply in relation to England only. Wales, Scotland and Northern Ireland are not covered by this page.