A section 20 notice is the first written step of the consultation an English landlord must run with leaseholders before major works or a long-term contract; skip the consultation and, for works, each leaseholder's contribution is limited to £250 unless a tribunal dispenses with the requirements. The works threshold is a contribution of more than £250 for any one leaseholder, the response windows are 30 days, and a notice of the reasons for the contract follows within 21 days of signing, unless the contractor was a nominated person (proposed by a leaseholder or the recognised tenants' association) or submitted the lowest estimate. Checked on 03.11.2026 against the Landlord and Tenant Act 1985 and SI 2003/1987 on legislation.gov.uk. England only. This is general information, not legal advice.

Who has to consult, and about what

The duty sits on "the landlord", the Act's word, and the people consulted are the "tenants", which in a block of flats means the leaseholders who pay a service charge, and a recognised tenants' association where one represents some or all of them. Which party is the landlord in your building depends on the lease and the ownership structure; this page does not look at that.

Two kinds of thing are consulted on. Qualifying works are "works on a building or any other premises". A qualifying long term agreement is "an agreement entered into, by or on behalf of the landlord or a superior landlord, for a term of more than twelve months" (s. 20ZA(2)), such as a multi-year contract. The regulations except some agreements (for example an employment contract), which this page does not list.

The thresholds

Section 20 applies "to qualifying works if relevant costs incurred on carrying out the works exceed an appropriate amount", and the regulations set that amount: "the appropriate amount is an amount which results in the relevant contribution of any tenant being more than £250" (reg. 6). For an agreement the line is £100 per leaseholder in an accounting period of twelve months (reg. 4(1)). As an illustration only: if ten flats share the cost of works equally, the £250 line is crossed once the works cost more than £2,500 in total; your lease may split costs differently, and one leaseholder with a large share can trigger it alone.

What happens if the consultation is skipped

Section 20(1) says the leaseholders' contributions are limited "unless the consultation requirements have been either" met or dispensed with by the tribunal. The limit for works is the prescribed amount: under s. 20(7) the contribution of a leaseholder whose share would otherwise exceed it "is limited to the amount so prescribed or determined", which with reg. 6 means £250. It is a ceiling on what can be recovered through the service charge. The sections read for this page name no fine.

The four stages for works (no public notice required)

Where public notice of the works is not required, the steps are in Part 2 of Schedule 4 to the regulations. Where it is required, Part 1 of the same Schedule applies instead and has no step for nominating contractors.

  1. Notice of intention (model notice, Word and PDF). "The landlord shall give notice in writing of his intention to carry out qualifying works" to each leaseholder and to a recognised tenants' association, if any. It must describe the works in general terms or say where and when a description can be inspected, give the landlord's reasons for considering the works necessary, invite written observations, state the address, the end date of the 30-day period, and invite each leaseholder and the association to propose a contractor to be asked for an estimate.
  2. Observations, then estimates. The landlord must have regard to the observations. It must try to obtain an estimate from a nominated person, obtain estimates, and prepare a statement of the estimated cost, giving the amounts for at least two estimates and summarising the observations with the landlord's response. At least one estimate must be from a person wholly unconnected with the landlord.
  3. Estimates on view. The landlord sends the statement to each leaseholder and the secretary of the association, and gives notice that says where and when the estimates can be inspected, and invites written observations on them within another 30 days. The landlord must have regard to what comes in.
  4. After the contract. Within 21 days of entering into the contract, the landlord gives notice of its reasons for awarding it, and, if observations were received, summarises them and responds. This step does not apply where the contractor was nominated or submitted the lowest estimate.

The windows are one rule: "means the period of 30 days beginning with the date of the notice", counted from the date on the notice. How a notice must be served on a leaseholder is not in the sections read, so follow the lease and the service rules.

Long-term agreements

A long agreement over the £100 line has its own route, in Schedule 1 (and Schedule 2 where public notice is required). This page does not walk through those stages; read Schedule 1 before using it.

If there is no time: dispensation

Under s. 20ZA(1) the landlord can apply to the tribunal, which "may make the determination if satisfied that it is reasonable to dispense with the requirements". The Act sets no list of reasons. What a tribunal treats as reasonable comes from decisions we did not read, so take advice before relying on it.

A separate rule: stale demands

Section 20B is not part of the consultation but is often met with it. A leaseholder is not liable to pay costs that "were incurred more than 18 months before a demand for payment of the service charge is served on the tenant", unless within those 18 months the leaseholder was notified in writing that the costs had been incurred and that a service charge would follow. Keep the date of the spend and the date of the demand together.

What this page does not say

It does not cover Wales, the Building Safety rules, the Leasehold and Freehold Reform Act 2024 (the legislation.gov.uk copy lists changes to section 20 by that Act and we did not work out which are in force), who counts as the landlord, service of notices, or case law. Check the current text before acting.

Where Unitify fits

Unitify does not serve a section 20 notice and is not connected to any court, tribunal or state system. It works around the process: lease documents, estimates and correspondence can be uploaded and kept with the building's documents (structured lease records are set up per project, not ready-made), you can enter each 30-day window and the 21-day contract notice as a ticket in the calendar, and post an announcement in the resident app on top of the legal notice, which stays the written notice served as the lease and the law require. Plans and prices are on the pricing page.

Book a demo

Sources

Topics:Section 20Service chargeLeasehold

Frequently asked questions

What is a section 20 notice?

The written notice of intention that a landlord in England gives to leaseholders (the Act says "tenants") before qualifying works, the first of the consultation stages in section 20 of the Landlord and Tenant Act 1985 and the Service Charges (Consultation Requirements) (England) Regulations 2003. It describes the works or says where a description can be inspected, gives the landlord's reasons, and invites written observations. Where public notice of the works is not required (Schedule 4, Part 2), it also invites leaseholders and a recognised tenants' association to propose contractors for an estimate; under Part 1 (public notice required) it says why no nominations are invited.

When does a landlord have to consult?

For works, when the cost means that any one leaseholder would have to contribute more than £250 (reg. 6). For an agreement lasting more than twelve months, when a leaseholder's share in an accounting period would be more than £100 (reg. 4(1)).

How long do leaseholders have to respond?

The regulations define the relevant period as "the period of 30 days beginning with the date of the notice". Observations, and under Part 2 the nominations of contractors, must be delivered within it after the first notice; the notice about the estimates opens a second 30-day window for observations only.

What happens if the landlord does not consult?

The leaseholders' contributions are limited. Section 20(1) says they are limited unless the requirements were complied with or dispensed with by the tribunal, and with works the limit is £250 per leaseholder. It is a cap on what can be recovered through the service charge; the sections read for this page name no fine.

Can the landlord ask a tribunal to waive the consultation?

Yes. Under section 20ZA(1) the tribunal "may make the determination if satisfied that it is reasonable to dispense with the requirements". The Act does not list what is reasonable, and this page does not say what tribunals have decided.

How many estimates must the landlord get?

Estimates, with a statement that gives the amounts of at least two of them, and at least one estimate must come from a person wholly unconnected with the landlord (Schedule 4, Part 2, para. 4). If a leaseholder or tenants' association nominated a contractor, the landlord must try to get an estimate from that person.

Does section 20 apply in Wales?

These regulations apply only in England. Wales has its own regulations, which this page does not cover.

Is a late service charge demand the same problem?

No, it is a different rule. Under section 20B a leaseholder is not liable for costs incurred more than 18 months before the demand, unless they were notified in writing within 18 months that the costs had been incurred and that a service charge would follow.